This final construction update includes a video of the new stadium. Click above to watch.Â
The turf work is finished. The bullpens are complete. The batting cages have been installed. The fence work is complete. The netting behind home plate has been installed. The windscreens for the outfield fence have been installed. Crews were taking down the construction fence on Tuesday (May 28). The field lighting is complete. The berm in right field has been formed. Work continues on the wiring of the press box. Netting infront of the dugouts and padding behind home plate will be installed over the summer. The videoboard will be installed by the start of the season next year.Â
As the construction of Chicago State University's new baseball stadium progresses, you can follow updated photos
here (updated May 28, 2013) or click through the photos below. Continue to check GoCSUCougars.com and the Chicago State baseball twitter feed of